The following construction projects are anticipated to affect highways in Highland County during the week of Oct. 9.
All outlined work is weather permitting. Projects with active or future traffic impacts are linked to OHGO.com.
NEW
State Route 41 Resurfacing - Work is set to begin Oct. 9 for a resurfacing project on S.R. 41 between S.R. 138 (Jefferson Street) and the Fayette County line. Work will occur daily from 7 a.m.-5 p.m., Monday through Friday. At least one lane of traffic will be maintained during work hours using flaggers. Estimated completion: fall 2023.
ONGOING
State Route 771 Resurfacing - Work has begun as of July 31 for a resurfacing project on S.R. 771 between S.R. 138 and the village of Leesburg. S.R. 771 will be reduced to one lane daily from 7 a.m.-5 p.m., Monday - Friday with traffic maintained using flaggers. Estimated completion: fall 2023.
State Route 41 Bridge Replacement - Work has begun as of July 10 for a bridge replacement on S.R. 41 between Birch Lane and the village of Greenfield. Principal construction on this project has been completed and the road is open to traffic as of Sept. 9. Remaining work will be completed using temporary lane closures with traffic maintained using flaggers as needed. Estimated completion: fall 2023.