Construction set for Ross-28 culvert replacement project

By
-
Construction Set For Ross-28 Culvert Replacement Project 
Contractors scheduled to begin operations next week 
CHILLICOTHE –  Construction to replace a large deteriorated culvert on state Route 28 in Ross County is slated to begin, with contractors closing the route to traffic early next week.
According to ODOT District 9 Deputy Director James A. Brushart, crews from RC Construction will close Ohio-28 on Monday, June 7, for a culvert replacement project at the route’s 7.08-mile marker. The project site is situated between County Road 59 (Harper Station Road) and Township Road 899 (Halley Lane), approximately seven miles east of the Ross-Highland County line, and construction also includes the installation of a retaining wall.
The closure is scheduled to be in effect for 45 days, and while the route is closed, motorists will be detoured via S.R. 41 at Greenfield to U.S. 50 at Bainbridge.
The RC Construction Company of Cutler, Ohio, was awarded a contract in the amount of $227,023 to replace the structure and install the retaining wall, and the scheduled completion date is Aug. 15. 
CHILLICOTHE –  Construction to replace a large deteriorated culvert on state Route 28 in Ross County is slated to begin, with contractors closing the route to traffic early next week.
According to ODOT District 9 Deputy Director James A. Brushart, crews from RC Construction will close Ohio-28 on Monday, June 7, for a culvert replacement project at the route’s 7.08-mile marker. The project site is situated between County Road 59 (Harper Station Road) and Township Road 899 (Halley Lane), approximately seven miles east of the Ross-Highland County line, and construction also includes the installation of a retaining wall.
The closure is scheduled to be in effect for 45 days, and while the route is closed, motorists will be detoured via S.R. 41 at Greenfield to U.S. 50 at Bainbridge.
The RC Construction Company of Cutler, Ohio, was awarded a contract in the amount of $227,023 to replace the structure and install the retaining wall, and the scheduled completion date is Aug. 15. 
[[In-content Ad]]

Add new comment

This is not for publication.
This is not for publication.

Plain text

  • No HTML tags allowed.
  • Lines and paragraphs break automatically.
  • Web page addresses and email addresses turn into links automatically.
Article comments are not posted immediately to the Web site. Each submission must be approved by the Web site editor, who may edit content for appropriateness. There may be a delay of 24-48 hours for any submission while the web site editor reviews and approves it. Note: All information on this form is required. Your telephone number and email address is for our use only, and will not be attached to your comment.